Procedure
D0110 Tall Pineapple
D0111 Fruit Basket
D0112 Gloria
D0113 Large Cherub
D0114 Tropicana
D0131 Narnia

A. Materials Needed
- Supplied with fountain: clear plastic hose, black rubber plug
(only for fountains where pump cord goes through the middle of the bowl);
pump and Kryton "Krystol Hydrostop" (if you purchased
these with the fountain)
- To be purchased: plumber's putty (building supply, hardware
store), household Vaseline (drugstore, pharmacy), pump and Kryton
sealer (if not purchased with fountain), and shims (e.g., pennies, washers,
anything that can be used to progressively raise a fountain part by
small increments)
B. Procedure
- Test the pump to make sure it is operational. A kitchen sink
filled with six inches of water is sufficient. Only plug the pump into
the electrical socket after the pump is submerged. Running a pump dry
will destroy it. Also, examine any control on the pump so that once
the pump is installed, you will know how to increase/decrease the water
flow. Removing a faulty pump is time-consuming.
- Touch up any scratches on the fountain pieces with touch up
stain. Let dry.
- After ensuring that every piece of the fountain is absolutely dry
(not in contact with rain/wet ground for several days,) water seal
every piece with Kryton sealer. Be sure to cover ALL sides of
every part, working methodically to ensure complete coverage.
- Prepare the area on which the fountain will stand. A concrete
pad or gravel base is fine. Ensure that the area is packed down and
reasonably level.
- Place the base of the fountain in the desired location and level
it by shimming the bottom. If the fountain is on a solid surface, make
sure the cord slot in the bottom of the base is pointed in the direction
you desire.
- Place the large bowl onto the base.
- Use three people to install the pump. Have two people tip the
large bowl and base together so that a third person can feed the pump
cord down through the bowl and base to the ground. Then, reaching under
the tipped base grasp the cord and pull it out from under the base,
ensuring that the cord lies in the channel in the bottom of the base
(otherwise, the fountain cannot be properly leveled.) When pulling the
cord through, leave about eight inches between the pump and the inside
of the large bowl.
- Make sure the walls of the white plastic pipe in the centre
of the fountain (through which the pump cord passes) are clean.
The black rubber plug needs to seat well into this pipe to prevent leakage.
- With some household Vaseline lightly coat all surfaces of the black
rubber plug. Open the slit in the side of the plug and place the
pump cord into the centre of the plug. Place the plug into the hole
in the fountain bowl, thus making a watertight seal around the pump
cord. Make sure the top of the plug is level with the top of the white
plastic pipe and that the slit in the plug is completely closed. Add
Vaseline to the top of the plug.
- Level the large bowl using either a 36-inch level or a straight
board with a smaller level. Shims (pennies, washers, etc.) must be used
under the bowl to get the top level.
- Place the split-ring pump housing into the large bowl and around
the pump. Turn the opening so that the pump is accessible but the opening
in the side is the least visible.
- Place the large finial on top of the pump housing.
- Connect the ½ inch plastic hose to the pump. The hose
should slide easily onto the nipple on the top of the pump.
- Depending upon the construction of the finial (pineapple, cherub,
etc.), either connect the other end of the plastic tubing to the copper
tube on the bottom of the finial, or run the plastic tubing up inside
the opening in the bottom of the finial.
- Make sure the plastic hose is still attached at the bottom to the
pump. Cut off any excess plastic hose.
- In the case where the plastic tubing goes all the way through a finial
and appears at the top, make sure the plastic hose is still attached
at the bottom to the pump. Then cut off any excess plastic hose.
- You may need to use a small amount of plumber's putty to seal
around the plastic tubing at the point it exits the finial (to keep
the water from running back down the inside of the fountain.)
- The "scuppers" are the indented areas in the edges of bowls
over which the water flows. For fountains D0112 and D0113,
put an extra coat of water sealer on the top and bottom edges
of each scupper. This will help to ensure water falls from each scupper
into the lower bowl, rather than running over the scupper and back under
the bowl (never falling at all.)
- Fill the fountain with room-temperature water. Cold water poured
into a warm fountain can cause the bowls to crack.
- Plug the pump into your source of electricity. Always use properly
grounded circuits and extension cords.
- Adjust leveling of pump house and finial to gain desired water distribution
from finial, and adjust pump for desired water flow.
- Reminder: Fountain bowls and pumps CANNOT BE
ALLOWED TO FREEZE WITH WATER IN THEM. If used in an unheated environment
(outdoors or unheated house), disassemble and store in winter. See manufacturer's
bulletin on "Care
and Maintenance" for more information.
C. Adjustments Commonly Needed
- Water does not flow evenly from scuppers around a bowl.
a. Check each individual scupper to make sure no excess concrete is
impeding water flow. Excess can be removed easily with a file or screwdriver.
b. Adjust shims to even out the water flow.
- Water does not flow out the top at all.
a. Make sure the plastic hose is not kinked at some point and that water
can flow freely from pump to finial.
b. Reach into the opening in the pump housing, gently pull the pump
to the opening and adjust the flow higher.
c. Check to see if pump is correct size. Pumps are rated by the height
they will raise a column of water. Under 24" need P-60 to P-80;
24" to 48" need P-140 to P-210; over 48" needs P-280
to P-380 or higher. Contact your pump supplier for accurate sizes. Remember,
it is not the height of the fountain, but the height from the pump to
the point where the water exits that must be measured.
d. The ID (inside diameter) of the plastic hose also affects the height
the water will rise. Any pump will push water higher in a 3/8"
hose than in a ½" hose, but more volume flows from a ½"
hose.
- Water flow is too heavy or fountain splashes too much.
a. Decrease the flow control on the pump.
b. Restrict the flow through the plastic hose. Many make-shift items
will work, e.g., a nail bent into a "U" shape with the hose
pressed inside it, a small hose clamp tightened around the hose, etc.
- Large bowl leaks at plug.
a. Make sure black rubber plug is pushed firmly into white plastic pipe
in the large bowl, so that the top of the plug is level with the top
of the pipe.
b. If necessary, remove the water from the large fountain bowl (a wet/dry
vacuum makes short work of this task), remove the black rubber plug
and check with your finger to ensure the walls of the white plastic
pipe are clean and free of cement. Clean the pipe (your fingernail is
often enough), re-Vaseline the plug with cord and insert the plug into
the pipe. When plug is seated properly (top of plug even with top of
white pipe and slit in plug completely closed,) apply extra Vaseline
to the top of the plug and the surrounding ¼" of white plastic
and concrete. Ensure the pump cord is snuggly fitted and that the slit
in the plug is tightly closed once seated in the pipe.
- Top bowl(s) fills but never spills over into the lower bowl.
a. Check to see if the water is actually running over the edges of a
top bowl, but then running under the lip of the bowl. If so, several
things can help.
(1) Increase the flow of the pump.
(2) Let the bowl dry and then apply Kryton water sealer to the
scuppers (indentations in the top of each bowl over which the water
flows.) The sealer encourages water not to "stick" to the
concrete and not to then run under the bowl instead of falling properly
into the bowl below.
(3) When dry, apply a small line of clear silicone (common bathroom
type from your building supply) about 3/16" thick under each scupper
right at the point where the water should fall. This small bead of silicone
will force the water to fall over it and will be invisible when the
fountain is running.
b. If water is NOT running over the edge of the bowl at all,
it is leaking through the centre around the plastic hose. Turn the fountain
off and re-seal the hole in the centre of the bowl (between the plastic
hose and the concrete) with more putty. It would not be wise to create
a permanent seal (glue, silicone, concrete) as the fountain could not
be disassembled for maintenance or moving.
- The plastic hose that came with the fountain does not fit onto
the pump purchased elsewhere.
a. Plastic hose is manufactured in sizes that allow one size to fit
snuggly inside the next larger size.
b. Measure the nipple on the top of your pump. That measurement is the
ID (inside diameter) of the plastic hose you need.
c. Usually ½" hose is supplied with the fountain. If the
pump needed 5/8", all you need is a short length (4") of 5/8"
hose from your building supply store. Insert that onto your pump, then
place the ½" hose down inside the top of the 5/8" hose
to complete the assembly.